METRONET STAGE 1 MORLEY ELLENBROOK LINE (MEL)

  • Water Corporation Relocation/Diversion Inground Services Enabling Works, and includes the following:
    • DN300 MSCL Water Distribution Main
    • DN355 PE Bore Main encased in a DN600 Concrete Sleeve
    • Abandoned DN535 reinforced concrete Sewer Pressure Main, removal.
    • DN500 MSCL Bore Main encased in a DN750 Concrete Sleeve
    • DN500 PE Bore Main
    • Abandoned DN400 MSCL pipe, removal.
    • Asbestos Removal and Clearance Works (140m existing DN450 AC pipe )
    • DN250 MSCL Water Reticulation Main encased in a DN450 Concrete Sleeve
    • Grout fill of redundant section of existing DN250 PVC-U water main.
    • Property Connections
    • Dewatering works required to complete works.
  • Installation of a Sewer Pump Station

CLIENT
Public Transport Authority of Western Australia

MANAGING CONTRACTOR
Laing O’Rourke Australia Construction

BUDGET
>$3,000,000

DURATION
Not Yet Complete