NINGALOO RESEARCH CENTRE, EXMOUTH

  • Installation of HDPE seawater pipelines
  • Installation of ICT conduit including cable pits
  • Rock Excavation
  • 2x 100,000 litre seawater tanks
  • 1x 20,000 Litre Filtered water tank
  • 3 x 5,000 litre storage tanks located on a mezzanine
  • Boiler & Chiller Heat Exchange
  • Install high-pressure air, ambient seawater, cooling and heating seawater loops and gas service pipework within a concrete culvert
  • Installation of all suspended pipework with the gantry and reticulated throught levels 1, 2 & mezzanine
  • Stormwater Stormcell system
  • Submersible pump station with fibreglass tank

CLIENT
The Minderoo Foundation Pty Ltd

MANAGING CONTRACTOR
The Minderoo Foundation Pty Ltd

BUDGET
>$4,000,000

DURATION
12 months