ARMADALE ROAD TO NORTH LAKE ROAD BRIDE

  • 1.6kms water reticulation including 11 property connections and 9 connections to existing infrastructure
  • DN500 Distribution MSCL Main including connections to existing Water Corporation Main
  • DN500 – DN750 Bore Main
  • Sewer Pressure Main including 2x connections to existing
  • Common Services Trenching
  • 4x Stormtec MC3500 tanks including associated piping & connections totaling 2,532,000L of stormwater storage

CLIENT
Main Roads WA

MANAGING CONTRACTOR
Armadale Access Alliance (Partnership between Laing O’Rourke Australia & BG&E)

BUDGET
>$3,000,000

DURATION
21 months